We are looking to strengthen our delivery team with Temporary Work Coordinator to lead the planning, coordination, design assurance, implementation, and removal of temporary works (TW) on our Wanlip STW site. You will ensure safety, compliance, and programme efficiency. Act as the focal point for all temporary works matters on the project and oversee the interface between the Temporary Works Designers(TWD), Temporary Works Supervisor(s) (TWS), construction team, and supply chain.
Governance & Coordination
- Maintain the Temporary Works Register, ensuring all items are identified, risk assessed, and controlled through their full lifecycle.
- Develop, implement, and enforce the Temporary Works Procedure for the project, aligned with company standards and BS 5975 principles.
- Ensure permits-to-load/unload are issued only after required inspections, design checks, and hold points are satisfied.
Design & Technical Assurance
- Prepare/brief TW Design Briefs, ensuring clear load cases, interfaces, constraints, and construction methodology are defined.
- Ensure as‑built information and design change controls are captured, approved, and recorded.
- Coordinate clash/interface management between TW and permanent works, utilities, plant, scaffolding, lifting ops, earthworks, and geotechnical risk.
Site Control & Execution
- Nominate/brief Temporary Works Supervisors and site teams; ensure they understand the design intent, inspection/test plans (ITPs), and hold points.
- Ensure TW are installed, inspected, maintained, monitored, adapted, and removed strictly in accordance with the design and procedures.
- Control change management: no deviation from design without formal approval; manage NCRs and corrective actions rapidly.
- Ensure TW are secured and signed against unauthorized alteration; manage weather and load monitoring where specified.
Safety, Risk & Compliance
- Integrate TW controls into lifting plans, excavation support, formwork falsework, temporary stability, access/edge protection, temporary services, temporary traffic/craneways, and temporary drainage/over‑pumping as relevant.
- Ensure compliance with CDM duties for design, coordination, and risk management; feed critical info to the Principal Designer and H&S File.
- Conduct site inspections, escalating hazards and blocking work if controls aren’t in place.
Documentation & Reporting
- Maintain: TW Register, design briefs, design/check certificates, TWS briefings, inspection records, permits, RFI logs, NCRs, handover/strike certificates, and as‑built records.
- Provide weekly status to PM: critical TW on path, upcoming hold points, design deliverables, resource pressures, and risks/opportunities.